← All postsHow-to

Adjudication: a decision in twenty-eight days, right or wrong

Adjudication gives construction disputes a fast binding decision. What it decides, the timetable, and why the answer sticks even when it is wrong.

How-toA

Adjudication is a statutory right in most construction contracts to refer a dispute to an independent adjudicator who must decide it within a short fixed period. The decision binds immediately and is enforced by the courts — and it can be reopened later, which almost never happens.

What adjudication decides

  • Any dispute arising under the construction contract, which is read broadly.
  • Payment disputes, which make up the large majority of referrals.
  • Extensions of time and the damages that follow from delay.
  • The valuation of variations and of work claimed as complete.
  • Whether the contract was validly terminated.
  • Not disputes under a contract that falls outside the statutory regime, where the right depends on the contract terms.

The timetable and why it is brutal

Twenty-eight days from referral to decision in the standard case, extendable only modestly and mostly with the referring party's consent. The referring party prepares its case for weeks in private, then serves it; the responding party may have a fortnight to answer a lever-arch file. That asymmetry is deliberate and lawful, and it is why the timing of a referral is a tactical decision in itself — a notice served the day before a holiday shutdown is a familiar manoeuvre.

A decision stands even if the adjudicator got the law wrong. Courts enforce on the basis that the parties agreed to a quick answer and can litigate the true position afterwards. Only a breach of natural justice or a decision outside the adjudicator's jurisdiction will prevent enforcement.

Why the answer usually sticks

  1. The decision is binding until finally determined by litigation, arbitration or agreement.
  2. Enforcement is by summary judgment and is usually granted within weeks.
  3. Challenging the merits later means funding a full case to recover money already paid.
  4. By then the commercial relationship is over and the appetite has usually gone.
  5. So in practice the adjudicator's answer becomes the final answer in most disputes.
  6. Which makes preparation before referral, not afterwards, the thing that decides outcomes.

Ettex Contracts keeps the contract, the notices and the payment history where they can be assembled quickly — the difference between answering a referral properly and answering it late. Where the project runs on a design and build contract, the same file has to show who took the design risk.

Frequently asked

How long does adjudication take?

Twenty-eight days from referral in the standard case, extendable only modestly and usually only with the referring party's consent.

Can a wrong decision be enforced?

Yes. Courts enforce even a legally wrong decision, on the basis that the parties agreed to a quick answer and can litigate the true position later.

Is the decision final?

Technically no — it binds until determined by litigation or arbitration. In practice very few are ever reopened.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.