Design and build: one contract, one party carrying the risk

Design and build makes the contractor responsible for both design and construction. What transfers, what does not, and where the model strains.

How-toD

Design and build is a procurement model in which one contractor takes responsibility for both designing and constructing the works. The appeal is a single point of responsibility — no argument between designer and builder about whose fault a defect is, because they are the same party.

What design and build transfers

  • Responsibility for completing the design from the employer's requirements.
  • Buildability risk, since the contractor cannot blame a design it produced.
  • Coordination between disciplines, which otherwise consumes the employer's time.
  • Usually a fixed price earlier in the process than traditional procurement allows.
  • Programme risk, where the contract makes the date an obligation rather than an aspiration.
  • Not the adequacy of the employer's requirements themselves, which stay with the employer.

What stays with the employer

The employer's requirements are the foundation of the whole arrangement, and errors in them remain the employer's problem. A requirement that is vague invites a contractor's proposal that meets it cheaply and lawfully; a requirement that is wrong produces a building that complies with the contract and does not work. This is the central tension of the model: the employer buys certainty by specifying outcomes in advance, at a stage when it often does not yet know exactly what it wants.

Novating the original design team is common and changes the dynamic completely. The architect who advised the employer now works for the contractor, and the employer loses independent design advice at the moment it most needs someone checking the contractor's proposals.

Where the model strains

  1. Late employer changes, which are expensive because the design is already committed.
  2. Quality, where the specification left room and the contractor chose the cheaper compliant option.
  3. Complex or heritage projects, where the design cannot sensibly be fixed early.
  4. Disputes over whether a change is a variation or was always required.
  5. Insurance gaps, since design liability under a construction policy differs from a designer's own cover.
  6. Payment and delay arguments, which end up in adjudication like any other construction dispute.

Ettex Records keeps the employer's requirements, the contractor's proposals and the change log in one place, which is what the variation argument always turns on months later.

Frequently asked

What does the contractor take on?

Completing the design, buildability, coordination and usually programme risk — but not errors in the employer's requirements.

What is novation?

Transferring the original design team to the contractor. It is common, and it costs the employer its independent design advice.

When is the model a poor fit?

Complex or heritage work where the design cannot be fixed early, and projects where the employer expects to make late changes.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.