Balance sheet reconciliation: proving the number, not just agreeing with it
A reconciled account is one where the balance is supported by evidence of what makes it up. Most accounts that look reconciled are merely explained.
A bill of quantities exists so competing tenders can be compared line for line. Its real value shows up later, when the work changes and someone has to price the change.
A bill of quantities is an itemised schedule of the materials, labour and works needed to build something, measured from the drawings and specification, with a quantity and a unit against every item and a space for the contractor to insert a rate. It is issued with the tender documents so that every bidder prices the same scope in the same order.
That comparability is the point. Without a bill, each tenderer measures the job themselves, and the client receives lump sums that cannot be compared — the cheapest may simply have missed something. With a bill, the client compares rate against rate and can see exactly where a bidder is expensive and where they are suspiciously cheap.
Descriptions have to be precise enough to price: the unit of measurement, the material, the finish, the constraint. "Blockwork, m²" is not pricable; the same item with thickness, block type, mortar and whether it is above or below ground is. Vague descriptions do not save time — they produce qualified bids and arguments later.
Quantities are measured under a standard method — NRM in the UK, CESMM for civil engineering, POMI or a local equivalent elsewhere — and the bill states which. The method decides what is measured net and what includes waste, what is deemed included in a rate, and how items are grouped. A bill that does not name its method leaves every rate open to a different reading.
A bill of quantities does not usually override the drawings and specification: those define the work, and the bill measures it. Where the contract makes the bill part of the contract documents, an error in quantity becomes a valuation matter rather than the contractor’s risk — which is exactly why the priority of documents clause is worth reading before tendering.
The third item is where money is won and lost. A rate that looked generous at tender becomes the price of every similar variation for the life of the job, and an unbalanced bill — high rates on early items, low on late ones — changes the contractor’s cash flow long before anyone notices.
A bill is a spreadsheet with a contractual life: it is priced by several people, revised during tender, then referenced for two years while the job runs. Ettex Sheets keeps the priced version, the addenda issued during tender and the measured quantities in one place with their history, so the rate someone quotes in a variation dispute can be traced to the version it came from. The same discipline that a bill of materials needs on the manufacturing side applies here — one schedule, versioned, not a folder of near-identical files.
Where the tender is run properly, the bill also sits at the centre of the procurement process: issued to all bidders at once, amended only by formal addendum, and returned priced in the same structure it went out.
Usually the quantity surveyor or cost consultant acting for the client, measuring from the design team’s drawings and specification. On design-and-build contracts the contractor may produce its own.
An estimate is the expected cost. A bill is a measured schedule of items with quantities but no prices until tenderers insert their rates — it is the instrument for obtaining prices, not a price itself.
It is the common abbreviation for bill of quantities, used interchangeably in tender documents and correspondence.
It depends on the contract form and the priority of documents clause. Under many traditional contracts it is a contract document, which affects who carries the risk of an error in quantity.
No. A provisional sum is an allowance for defined work that will happen but is not yet detailed. A contingency is an allowance for the unforeseen and is not attached to any item of work.
A reconciled account is one where the balance is supported by evidence of what makes it up. Most accounts that look reconciled are merely explained.
A borrowing base certificate is a periodic calculation, not a report. The eligibility rules that shrink the collateral pool are where most of the work lives.
The DMR is what a competent stranger would need to build the device correctly. If it points at documents that no longer exist at that revision, it is not a recipe.