Defects liability period: the year after the building is finished

The defects liability period is when the contractor must return to fix faults. How long it runs, what counts as a defect, and what happens at the end of it.

How-toD

The defects liability period is the stretch after a building is handed over during which the contractor remains obliged to come back and put right faults that appear. It is not a warranty on the building and it is not the end of the contractor's liability — two misunderstandings that cause most of the arguments in it.

How the defects liability period works

  • It starts at practical completion, not at the end of the works on site.
  • It runs for a stated term, commonly twelve months, longer for mechanical and electrical elements in some contracts.
  • Defects appearing in that window are notified to the contractor, who returns to remedy them.
  • The contractor has a right to return and fix, which means engaging somebody else and sending the bill is usually a breach.
  • A schedule of defects is issued at or near the end, consolidating outstanding items.
  • A certificate of making good follows once they are remedied, which releases the remaining retention.

What counts as a defect

Work that does not comply with the contract — wrong materials, poor workmanship, something that does not perform as specified. Not damage caused by the occupier, not ordinary wear, and not items that were always going to need maintenance: a filter that needs changing is not a defect, however much the occupier would like it to be. The grey area is latent failure of something installed correctly but of poor quality, and that argument is settled by the specification rather than by expectation.

The period ending does not end the contractor's liability. It ends the right and obligation to return and fix. Claims for defective work remain available for the full limitation period afterwards, which is measured in years and depends on whether the contract was executed as a deed.

What happens at the end

  1. Inspect properly before the period expires, since a defect found a week late is a different conversation entirely.
  2. Issue the schedule of defects within the time the contract allows, which is often short.
  3. Allow access and a reasonable opportunity to remedy, and record when it was offered.
  4. Where the contractor fails to return, follow the contractual route before employing others.
  5. Obtain the certificate of making good, which is what unlocks the retention balance.
  6. Record which defects were remedied and how, because recurrence is the start of a larger claim.

Ettex Contracts keeps the certificate dates, the defects schedule and what was done about each item, so the end of the period is a scheduled event rather than something noticed afterwards. The retention balance that depends on it belongs in the same place.

Frequently asked

When does the defects liability period start?

At practical completion, and it typically runs twelve months — sometimes longer for mechanical and electrical elements.

Can the employer hire someone else to fix a defect?

Usually not without following the contract first. The contractor generally has a right to return and remedy, and bypassing it is a breach.

Does liability end when the period ends?

No. The obligation to return and fix ends, but claims for defective work remain available for the full limitation period.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.