Practical completion: the moment risk changes hands

Practical completion marks a building as fit for its purpose despite minor defects. What it triggers, who decides, and why the certificate date matters so much.

How-toP

Practical completion is the point at which building work is treated as finished for contractual purposes — not perfect, but usable for its intended purpose with only minor items outstanding. It is a single date on a certificate, and an unusual number of financial consequences hang off it.

What practical completion triggers

  • Possession passes to the employer, who can occupy and use the building.
  • Risk and insurance responsibility transfer, which is why the date must be unambiguous.
  • The defects liability period starts running, with its own end date.
  • Liquidated damages for delay stop accruing, which is usually the contractor's main interest in it.
  • Half the retention is typically released, with the balance held until defects are made good.
  • The limitation period for certain claims begins.
  • Any contractual handover obligations fall due: warranties, manuals, as-built drawings and test certificates.

Who decides, and on what basis

Normally the contract administrator or architect, exercising judgement rather than applying a checklist — and that judgement is about whether the works can be used for their purpose, not whether the snagging list is empty. A building with a long list of cosmetic items can be practically complete; one with a non-functioning lift or no fire alarm commissioning usually cannot, however short the list. Disputes almost always come from the employer treating practical completion as «everything done» and the contractor treating it as «close enough».

Do not accept handover without the documentation. Test certificates, commissioning records and as-built drawings are far harder to obtain once the contractor has been paid and left site, and their absence surfaces years later when a building control or insurance question arrives.

Why the certificate date matters

  1. It fixes when damages stop, which can be a substantial daily figure.
  2. It starts the defects period, so a date recorded late shortens the contractor's obligation in practice.
  3. It determines insurance transfer, and a gap between policies is the classic expensive oversight.
  4. It governs retention release timing.
  5. It is the reference point for any later claim about when work was completed.
  6. Record it in writing with the certificate, not by email agreement that nobody can find.

Ettex Contracts keeps the certificate with the defects list, the handover documents and the retention dates, which is what makes the end of a project answerable rather than reconstructed. The condition record taken before work started belongs in the same file.

Frequently asked

What does practical completion mean?

The works are fit for their intended purpose with only minor items outstanding — not that everything is finished to perfection.

What does it trigger?

Transfer of possession and risk, the start of the defects liability period, the end of liquidated damages and usually release of half the retention.

Can it be certified with outstanding items?

Yes, if they are minor. A long cosmetic snagging list can still be practically complete; missing fire alarm commissioning generally cannot.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.