An extension of time shifts the contractual completion date. What qualifies, why notices matter more than merit, and how concurrent delay complicates it.
An extension of time moves the contractual completion date when delay is caused by something the contract puts at the employer's risk. Its first purpose is not fairness to the contractor — it is protecting the employer's right to deduct damages, which collapses entirely if time cannot be extended when the employer causes delay.
Most contracts require notice within a stated period of the delay becoming apparent, with particulars following. A contractor with an unanswerable entitlement who gives notice late may lose it entirely under a condition precedent, while one with a marginal claim who follows the procedure gets it considered. That strikes people as unjust and it is how the contracts are written — the purpose is to let the employer respond while mitigation is still possible, rather than receive a claim at the end of the job.
Granting an extension is in the employer's interest, not a concession to the contractor. Refusing one for employer-caused delay risks setting time at large, which removes the completion date and the liquidated damages with it — a far worse outcome than the weeks that were in dispute.
Ettex Contracts keeps the notices with their dates, the instructions that caused delay and the programme revisions, which is the chain any extension claim stands on. The site diary that evidences what happened each day belongs with it.
To protect their own right to liquidated damages. Refusing one for employer-caused delay can set time at large and remove the completion date entirely.
Yes. Where notice is a condition precedent, a late notice can defeat an otherwise unanswerable entitlement.
Where an employer risk event and a contractor risk event cause the same delay. Treatment varies by contract, and programme records decide it in practice.
Leasehold is the right to occupy for a term under a lease. What the term means for value, the obligations imposed, and what happens at the end.
A locked box sets the price from historic accounts with no post-closing adjustment. How leakage is controlled, who carries risk, and when it suits.
An asset sale transfers selected assets rather than the company. What can be left behind, what cannot, and why it takes longer.