Extension of time: moving the completion date lawfully

An extension of time shifts the contractual completion date. What qualifies, why notices matter more than merit, and how concurrent delay complicates it.

How-toE

An extension of time moves the contractual completion date when delay is caused by something the contract puts at the employer's risk. Its first purpose is not fairness to the contractor — it is protecting the employer's right to deduct damages, which collapses entirely if time cannot be extended when the employer causes delay.

What qualifies for an extension of time

  • Variations instructed by the employer, which add work the programme never allowed for.
  • Late information, access or possession of the site.
  • Exceptionally adverse weather, where the contract lists it and the threshold is evidenced.
  • Statutory undertakers and other parties outside the contractor's control.
  • Suspension for non-payment, where the regime permits it.
  • Force majeure events as the contract defines them, which is narrower than people assume.
  • Not contractor-caused delay, and not inefficiency dressed up as an external event.

Why notices matter more than merit

Most contracts require notice within a stated period of the delay becoming apparent, with particulars following. A contractor with an unanswerable entitlement who gives notice late may lose it entirely under a condition precedent, while one with a marginal claim who follows the procedure gets it considered. That strikes people as unjust and it is how the contracts are written — the purpose is to let the employer respond while mitigation is still possible, rather than receive a claim at the end of the job.

Granting an extension is in the employer's interest, not a concession to the contractor. Refusing one for employer-caused delay risks setting time at large, which removes the completion date and the liquidated damages with it — a far worse outcome than the weeks that were in dispute.

How concurrent delay complicates it

  1. Concurrent delay is where an employer risk event and a contractor risk event both cause the same period of delay.
  2. Approaches differ: some give full extension without money, others apportion, some give nothing.
  3. What the contract says governs, and many standard forms are silent — which is why the dispute exists.
  4. Programme records decide it in practice, not legal theory.
  5. Keep a baseline programme and update it, since without one causation cannot be demonstrated either way.
  6. Record what actually happened daily, because retrospective reconstruction persuades nobody.

Ettex Contracts keeps the notices with their dates, the instructions that caused delay and the programme revisions, which is the chain any extension claim stands on. The site diary that evidences what happened each day belongs with it.

Frequently asked

Why do employers grant extensions of time?

To protect their own right to liquidated damages. Refusing one for employer-caused delay can set time at large and remove the completion date entirely.

Can a valid claim fail on procedure?

Yes. Where notice is a condition precedent, a late notice can defeat an otherwise unanswerable entitlement.

What is concurrent delay?

Where an employer risk event and a contractor risk event cause the same delay. Treatment varies by contract, and programme records decide it in practice.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.