A site diary is the daily record of what happened on a construction site: who was there, what was done, what stopped, and what the conditions were. It is kept because memory fails and because claims arrive months later, and the diary written contemporaneously is worth more than any reconstruction however honest.
Because exceptionally adverse weather is one of the few grounds for extension of time in most standard contracts, and establishing it requires a daily record compared against a baseline. A diary saying «rain» for three weeks proves far less than one recording hours lost, which trades were affected and what work was impossible. The same logic applies to anything else that stops progress: the entry that helps is the one specific enough to be tested.
Write it the same day, on site. A diary completed weekly from memory is visibly that, and in a dispute the other side will say so — contemporaneous records carry weight precisely because they could not have been written with the argument in mind.
Daily records and statutory checks sit side by side on site. A scaffold inspection is required before first use, at weekly intervals and after any weather event that could affect stability.
Ettex Notes suits the diary as a dated entry per day, written on site rather than typed up later, with photographs attached to the same record. Instructions and variations that arise from it belong in the project documentation, where they can be tracked against what was agreed.
Labour by trade, plant present, work completed, weather as observed, delays, instructions, visitors and deliveries — recorded the same day.
Because exceptionally adverse weather supports extension of time, and that requires hours lost and trades affected rather than a single word per day.
It carries far less weight. Contemporaneous records matter precisely because they could not have been written with a later argument in mind.
A shift handover transfers knowledge between teams who never meet. What it must contain, why verbal-only fails, and how to keep it short enough to happen.
Knowledge capture fails as a documentation project and works as a habit attached to real work. Where to start, what to skip, and why the expert is the wrong person to write it.
A decision log records what was decided, by whom, and what was rejected. The format that takes two minutes, and why the rejected options are the part worth keeping.