Site diary: the daily record that settles construction disputes

A site diary records what happened on site each day. What to capture, why weather matters, and how it becomes evidence in a delay claim.

How-toS

A site diary is the daily record of what happened on a construction site: who was there, what was done, what stopped, and what the conditions were. It is kept because memory fails and because claims arrive months later, and the diary written contemporaneously is worth more than any reconstruction however honest.

What a site diary should capture each day

  • Labour on site by trade and number, which is the basis of any disruption claim.
  • Plant and equipment present, including anything standing idle and why.
  • Work completed, in enough detail to locate it — area, level, element.
  • Weather, recorded as observed rather than from a forecast, with times if it changed.
  • Delays, instructions received, and anybody who visited — client, inspector, designer.
  • Deliveries received and anything rejected, which is where materials disputes start.

Why weather is recorded so carefully

Because exceptionally adverse weather is one of the few grounds for extension of time in most standard contracts, and establishing it requires a daily record compared against a baseline. A diary saying «rain» for three weeks proves far less than one recording hours lost, which trades were affected and what work was impossible. The same logic applies to anything else that stops progress: the entry that helps is the one specific enough to be tested.

Write it the same day, on site. A diary completed weekly from memory is visibly that, and in a dispute the other side will say so — contemporaneous records carry weight precisely because they could not have been written with the argument in mind.

Daily records and statutory checks sit side by side on site. A scaffold inspection is required before first use, at weekly intervals and after any weather event that could affect stability.

How it becomes evidence

  1. Keep entries factual and avoid opinion about fault, which weakens rather than strengthens the record.
  2. Sign and date each day, ideally by the person who was present rather than an office manager.
  3. Photograph progress and reference the photographs in the entry, since a numbered image is locatable later.
  4. Record instructions given verbally, because those are exactly the ones later disputed.
  5. Keep the diary even when the job runs smoothly, as the gaps are what get questioned.
  6. Retain it for the period claims remain possible, which is usually far longer than the job itself.

Ettex Notes suits the diary as a dated entry per day, written on site rather than typed up later, with photographs attached to the same record. Instructions and variations that arise from it belong in the project documentation, where they can be tracked against what was agreed.

Frequently asked

What should go in a site diary?

Labour by trade, plant present, work completed, weather as observed, delays, instructions, visitors and deliveries — recorded the same day.

Why does weather need such detail?

Because exceptionally adverse weather supports extension of time, and that requires hours lost and trades affected rather than a single word per day.

Does a diary written weekly still count?

It carries far less weight. Contemporaneous records matter precisely because they could not have been written with a later argument in mind.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.