← All postsHow-to

Payment notice: the document that fixes what is due

A payment notice states what is payable and why. The notice regime, what happens when one is missed, and why a pay less notice has a deadline.

How-toP

A payment notice states the sum a paying party considers due and the basis for calculating it. In construction payment regimes it is not administrative courtesy — it is the mechanism that fixes the amount, and missing it can oblige you to pay a figure you never agreed.

What a payment notice must contain

  • The sum the payer considers due at the payment due date.
  • The basis on which that sum is calculated, in enough detail to be understood rather than asserted.
  • Issued within the period the contract or statute specifies, counted from the due date.
  • Issued even where the sum considered due is nil, which is the step most often skipped.
  • From the payer or a specified person such as the contract administrator.
  • In writing, by the method the contract requires, with evidence of when it was sent.

What happens when one is missed

The application becomes the notified sum. Where the payer fails to issue a payment notice in time, the contractor's application for payment typically becomes the amount due in full — not the amount that should have been due, and not subject to later argument about valuation. These are commonly called smash and grab claims, and they succeed on the procedural failure alone. The merits of the valuation can be revisited later in a true value adjudication, but the money usually has to be paid first, which is a serious cash problem for the payer.

Nil notices still count. A payer who believes nothing is due must say so in a valid notice within the period — silence is not a nil assessment, it is a missed notice, and the consequences are the same as if the payer had agreed the application.

Why the pay less notice has its own deadline

  1. It is the mechanism for paying less than the notified sum, for example after a deduction or set-off.
  2. It must be issued not later than a prescribed period before the final date for payment.
  3. It must state the sum considered due and the basis of calculation, like the payment notice.
  4. Late is the same as absent: the notified sum becomes payable in full.
  5. Deductions announced only in correspondence or by phone do not satisfy it.
  6. Diarise both deadlines from the payment due date at the start of the contract, not per cycle.

Ettex Invoices can carry the due dates and notice deadlines alongside each application, so a missed notice becomes visible before the deadline rather than after. The valuation behind each notice belongs in the same record, since a true value dispute starts from it.

Frequently asked

What must a payment notice state?

The sum the payer considers due and the basis of its calculation, issued within the contractual or statutory period — even if that sum is nil.

What happens if the payer misses it?

The contractor's application typically becomes the sum due in full, payable regardless of its merits, with valuation arguments deferred to a later adjudication.

What is a pay less notice?

The way to pay less than the notified sum. It has its own deadline before the final date for payment, and late is treated the same as absent.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.