Rebate agreement: discounts paid after the fact
A rebate agreement returns money once volume targets are met. How tiers work, the accounting trap, and what makes rebates uncollectable.
A payment notice states what is payable and why. The notice regime, what happens when one is missed, and why a pay less notice has a deadline.
A payment notice states the sum a paying party considers due and the basis for calculating it. In construction payment regimes it is not administrative courtesy — it is the mechanism that fixes the amount, and missing it can oblige you to pay a figure you never agreed.
The application becomes the notified sum. Where the payer fails to issue a payment notice in time, the contractor's application for payment typically becomes the amount due in full — not the amount that should have been due, and not subject to later argument about valuation. These are commonly called smash and grab claims, and they succeed on the procedural failure alone. The merits of the valuation can be revisited later in a true value adjudication, but the money usually has to be paid first, which is a serious cash problem for the payer.
Nil notices still count. A payer who believes nothing is due must say so in a valid notice within the period — silence is not a nil assessment, it is a missed notice, and the consequences are the same as if the payer had agreed the application.
Ettex Invoices can carry the due dates and notice deadlines alongside each application, so a missed notice becomes visible before the deadline rather than after. The valuation behind each notice belongs in the same record, since a true value dispute starts from it.
The sum the payer considers due and the basis of its calculation, issued within the contractual or statutory period — even if that sum is nil.
The contractor's application typically becomes the sum due in full, payable regardless of its merits, with valuation arguments deferred to a later adjudication.
The way to pay less than the notified sum. It has its own deadline before the final date for payment, and late is treated the same as absent.
A rebate agreement returns money once volume targets are met. How tiers work, the accounting trap, and what makes rebates uncollectable.
Quantum meruit allows payment for work done where no price was agreed. When it applies, how the sum is assessed, and why it is a last resort.
Deferred revenue is cash collected for work not yet delivered. Why it is a liability, how it unwinds, and what it hides about a business.