Construction RFI: writing RFI forms that get clear answers fast

A construction RFI resolves a gap or conflict in the design documents. What a good RFI form contains, how to log and track responses, and how to keep RFIs from delaying work.

How-toC

A construction RFI — request for information — is a formal question from the contractor to the design team when drawings or specifications are unclear, incomplete or in conflict. It creates a written record of the question, the answer and its date, which matters when the answer changes cost or programme. Projects routinely raise hundreds of RFIs; the difference between a manageable process and a source of delay is how well each RFI is written and tracked.

What a construction RFI form should contain

  • RFI number, date raised, and the date a response is needed by.
  • The specific drawing, detail or specification clause concerned, with revision.
  • A single, clear question — one issue per RFI.
  • The contractor's proposed solution, where one exists.
  • Sketches, photographs or marked-up extracts showing the problem.
  • Potential impact on cost and programme if the answer is delayed.
  • Response section: answer, responder, date, and whether it constitutes a change.

Write RFIs that can be answered

  1. Check the documents first — many RFIs ask questions the specification already answers.
  2. Ask one question per RFI; bundled questions get partial answers.
  3. Reference exactly where the conflict is, not "see drawings".
  4. Propose an answer where you can; a yes or no is faster than an open question.
  5. State the date the answer is needed and why, tied to the programme.
  6. Avoid using RFIs to request changes — that is what a variation or change request is for.

An RFI answer that changes scope, cost or time is a change, not information. Flag it as such when it comes back, or the cost impact disappears into the RFI log.

RFI form and RFI log

The form captures the question; the log tracks every RFI's status. Ettex Forms is a practical way to raise the RFI with required fields and attachments, and each submission lands in Ettex Records as a row in the RFI log with status, responder and dates. That makes the questions that matter in a project meeting — what is overdue, what is waiting on which consultant, which answers created changes — a filter rather than a spreadsheet exercise.

RFIs in project management terms

  • Track average response time by consultant; it predicts where delays will come from.
  • Review open RFIs weekly against the programme.
  • Link RFIs to the submittal log and to any resulting variation order.
  • Look for clusters of RFIs on the same area — they usually signal a coordination problem in the design.
  • Close RFIs formally, including those withdrawn or superseded.

Frequently asked

How long should an RFI response take?

The contract usually sets it — often five to ten working days. Where it does not, agree a standard at the start of the project and record it in the RFI procedure.

What is the difference between an RFI, an RFP and an RFQ?

In construction, an RFI asks for clarification of design information. An RFP requests proposals and an RFQ requests prices — both are procurement documents, not project queries.

Can an RFI response be treated as an instruction?

Only if the contract says so. Many contracts require a separate instruction or variation for any change, even when the RFI answer describes it.

IP
Written by Ivan P.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.