Loss and expense is the contractual route by which a contractor recovers the cost of delay and disruption caused by the employer. It sits alongside extension of time and is frequently confused with it — time relieves the contractor of damages for lateness, money compensates for what the lateness cost.
A relevant matter under the contract, an actual loss, and a causal link between them — and the link is where most claims fail. Records contemporaneous with the events carry the argument: allocation sheets showing which gang worked where, plant returns, instructions received and when. A claim built after completion from a spreadsheet of totals invites the response that the figures are a reconciliation rather than proof. Where the work fell entirely outside the contract, the position changes and a quantum meruit claim may arise instead, assessed on reasonable value rather than contractual entitlement.
Extension of time is not automatic entitlement to money, and money is not automatic on an extension. The two are assessed separately, under different clauses and often on different relevant events — a point lost in most negotiations.
Where the events cannot be separated at all, a contractor may be driven to advance a global claim instead, attributing the whole overrun to the employer collectively. Tribunals accept that only where disentangling the causes is genuinely impracticable.
Ettex Sheets suits the cost allocation behind a claim — labour, plant and preliminaries tied to the events that caused them — which is what converts an assertion into a provable figure.
No. An extension relieves the contractor of damages for lateness; loss and expense compensates for what the delay cost. They are assessed separately.
Late notice and absent contemporaneous records. Causation has to be shown event by event, not reconciled at the end.
Generally only where the contract expressly provides for it.
Debt finance funds a business through borrowing repaid with interest. What lenders require, what it costs beyond the rate, and when it is wrong.
Completion accounts adjust the price using accounts drawn up after closing. How the mechanism works, what gets disputed, and how to narrow it.
Indexation ties contract prices to a published index. Which index to choose, the caps that matter, and why it rarely matches real costs.