Loss and expense: recovering the cost of disruption

Loss and expense compensates a contractor for employer-caused delay and disruption. What it covers, what must be proved, and why notices decide it.

How-toL

Loss and expense is the contractual route by which a contractor recovers the cost of delay and disruption caused by the employer. It sits alongside extension of time and is frequently confused with it — time relieves the contractor of damages for lateness, money compensates for what the lateness cost.

What loss and expense covers

  • Prolongation: site establishment, supervision and plant held for longer than planned.
  • Disruption: labour working less efficiently than it would have done, which is harder to prove.
  • Head office overheads attributable to the extended period.
  • Finance costs on money tied up longer than anticipated.
  • Increased preliminaries where the programme is extended.
  • Not loss of profit, unless the contract provides for it.
  • Not costs the contractor would have incurred anyway.

What has to be proved

A relevant matter under the contract, an actual loss, and a causal link between them — and the link is where most claims fail. Records contemporaneous with the events carry the argument: allocation sheets showing which gang worked where, plant returns, instructions received and when. A claim built after completion from a spreadsheet of totals invites the response that the figures are a reconciliation rather than proof. Where the work fell entirely outside the contract, the position changes and a quantum meruit claim may arise instead, assessed on reasonable value rather than contractual entitlement.

Extension of time is not automatic entitlement to money, and money is not automatic on an extension. The two are assessed separately, under different clauses and often on different relevant events — a point lost in most negotiations.

Where the events cannot be separated at all, a contractor may be driven to advance a global claim instead, attributing the whole overrun to the employer collectively. Tribunals accept that only where disentangling the causes is genuinely impracticable.

Why notices decide the outcome

  1. Most contracts require notice within a stated period of the matter becoming apparent.
  2. Late notice can bar the claim entirely, regardless of merit.
  3. Updates are usually required as the effect unfolds, not only at the start.
  4. The claim should be reflected in each payment notice cycle rather than saved for the final account.
  5. Quantification follows entitlement, so establish the right before arguing the number.
  6. Keep the records as the work proceeds, since reconstruction is both expensive and unconvincing.

Ettex Sheets suits the cost allocation behind a claim — labour, plant and preliminaries tied to the events that caused them — which is what converts an assertion into a provable figure.

Frequently asked

Is loss and expense the same as an extension of time?

No. An extension relieves the contractor of damages for lateness; loss and expense compensates for what the delay cost. They are assessed separately.

What usually defeats a claim?

Late notice and absent contemporaneous records. Causation has to be shown event by event, not reconciled at the end.

Is loss of profit recoverable?

Generally only where the contract expressly provides for it.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.