Retention release: getting the last money out of a project

Retention is money withheld until defects are made good. How the two releases work, the deadlines that are missed, and what to do when it is not paid.

How-toR

Retention is a percentage of each payment withheld by the employer as security that defects will be put right. For the contractor it is the last money on a job and the hardest to collect, because by the time it falls due everyone has moved on to other projects and nobody is chasing it.

How retention release works

  • A percentage, commonly three to five, is deducted from each interim payment.
  • Half is typically released at practical completion, when the building becomes usable.
  • The remaining half is released at the end of the defects liability period, once outstanding items are made good.
  • Release usually requires a certificate rather than happening automatically, which is the step most often forgotten.
  • The money remains the employer's to hold unless the contract puts it in a separate trust account.
  • Deductions may be made for defects not remedied, but should be substantiated rather than asserted.

The deadlines that get missed

Almost all of them, in practice. The defects period ends quietly, the final certificate is nobody's priority, and the subcontractor three tiers down has no visibility of any of it. Retention commonly goes unclaimed simply because the person who would chase it left the company, and the figure is small enough individually and large enough in aggregate to matter badly to a subcontractor's cash position. Diarising both release dates at the moment the contract is signed is the entire discipline, and it is rarely done.

In an insolvency up the chain, retention held in the main contractor's general funds is usually unsecured — you join the queue. Where the contract allows a trust account, asking for one at negotiation costs nothing and is worth more than any clause about payment timing.

Money is not the only thing outstanding at the end of a job. A collateral warranty gives a funder, buyer or tenant a direct claim against people they never engaged, and collecting them late is far harder than making delivery a condition of payment.

When it is not paid

  1. Check what the contract actually requires: certificate, notice, or application.
  2. Submit the application in the prescribed form and on time, since an informal request may not start any clock.
  3. Record the defects you were asked to remedy and the date you completed them.
  4. Escalate in writing with the contractual deadline stated, which changes the tone of the conversation.
  5. Use the statutory payment and adjudication routes where they exist — they are fast and designed for exactly this.
  6. Track aged retention alongside aged debt, because it disappears from view otherwise.

Ettex Invoices can carry retention as its own line with both release dates, so the amount outstanding and when it falls due stay visible rather than vanishing into a completed project. The defects record that unlocks the second half belongs with it.

Frequently asked

When is retention released?

Typically half at practical completion and half at the end of the defects liability period, usually against a certificate rather than automatically.

Why does retention go unclaimed?

The release dates pass quietly, the people who knew about them move on, and nothing in the system surfaces the amount as still owed.

What if the employer becomes insolvent?

Unless the contract requires a separate trust account, retention held in general funds is usually an unsecured claim.

MI
Written by Maria I.

Part of the Ettex team — writing about product, engineering and the future of work.

More posts
Get the best of the Ettex blogProduct news, guides and tips — straight to your inbox, no spam.